MSA Professional Services, the City’s engineering consultant, advised that they submitted a “Notice of Intent” to award this project to Visu-Sewer with teh reqeust they enter into a good faith dialogue to discuss methods to reduce inflow into the sanitary sewer that runs along the west side of Bellingham Roadway.

Ideas being discussed include lining the sanitary sewer as well as putting a cap on the number of hours the excavator utilizes to look for santiary laterals.

The City Council approved the low bid on this project of $160,921.50 from Visu-Sewer, Inc. The approved bid is nearly $50,000 more than the estimated price – primarily due to estimated costs for exploratory investigation of sanitary sewer lateral lines off of Bellingham Road. 

MSA recommended approving the bid and then continuing to negotiate alternative methods of investigating/dealing with the sewer lines off of Bellingham Road that, if approved, will reduce the total project price to bring it more in line with the initial project estimate.

MSA Professional Services reported to the City Council that the bid opening for this project occured on January 21 at 2pm (as scheduled), but the low bid was significantly higher than MSA’s budgeted construction costs of $116,800.

The reason for the cost variance was related to the exploratory excavation for sanitary laterals located near Bellingham Road. MSA advised the Council that the firm would continue exploring ways to proceed with an award and simultaneously lower the project cost without committing any bidding violations.

As things currently stand, the work is still expected to take place this summer.

According to MSA Professional Services, the project has been advertised for bid. The public hearing is scheduled for January 14 at 7pm. A non-mandatory, pre-bid meeting has been held. 

The bid opening is scheduled for January 21, 2020 at 1:30 pm. MSA’s opinion of the probable cost of construction on thisp roject is $116,800.

The Riverdale City Council approved the preparation of plans and specs for bids in the coming months. The process will be overseen by MSA Professional Services as part of their contract with the City.

A copy of the resolution authorizing MSA to seek bids on the project can be found here.

This project is estimated to cost the City of Riverdale $116,800 and should be completed during the summer of 2020. Sanitary sewer work will be performed in the Havens Acres neighborhood and on Fenno and Valley Drives.

At a meeting held earlier in the day, MSA discussed the following items on this project with the City:

•    Plans, specifications and an engineer’s opinion of the probably construction cost have been submitted to the City for approval. The Iowa DNR has issued a permit for the project. A GP#2 permit is not required.

•    The City needs to schedule a public hearing for this project.

•    MSA recommends a winter 2020 bid letting.

MSA Professional Services reported to the City Council that they have obtained the project permit from Iowa DNR and now seeks bidding guidance from the City on this project.

MSA Professional Services reported to the City Council that they are currently working on a timeline for bidding this project with Administrator Tim Long.

MSA Professional Services reported to the City Council that they have applied for a project permit from the Iowa DNR so work can begin this spring. The project is currently in the cue for bidding in January of 2020.

Project Details:

Scope of Work:

The sub-contractor will be expected to supply all labor, equipment and materials to seal and rehabilitate identified sanitary I&I points in the southern part of Riverdale.

Budget:

$160,921.50 (may be revised downward)

Public Hearing Date

Completed

Project Bid Date:

Completed

Project Start Date:

June, 2020

Project Completion Date:

August, 2020

 

 

%

Percent Complete