The Riverdale City Council authorizes MSA Professional Services to begin the bid preparation process for the Havens Acres Roadway Rehabilitation Project. A copy of the resolution can be found here.

According to paperwork provided by MSA, the budget for the project is $228,200 and should be completed during the summer of 2020.  

Construction schedules and traffic concerns for the Havens Acres neighborhood will be discussed with residents at an upcoming neighborhood meeting in January.

The City’s engineering firm, MSA Professional Services, updated the City Council that plans were 95% complete and ready for the bidding process which is expected to take place in January of 2020. Work should commence on this project later on that calendar year.

Project Details:

Scope of Work:

The sub-contractor will be expected to supply all labor, equipment and materials to rehabilitate roadways on Wisteria and Kensington Street.

Budget:

$228,200

Public Hearing Date:

January 14, 2020

Project Bid Date:

Bids due by January 20, 2020
Bids opened on January 21, 2020
MSA recommendations on January 23, 2020
Council awards bid on January 28, 2020

Project Start Date:

On or after June 8, 2020

Project Completion Date:

6 to 8 weeks after start of construction (late-July/early-August)

 

 

%