This weekend, letters were sent to residents of Havens Acres providing the first details on the planned roadway rehabilitation project for the area. The project will deal with several of the issues resulting from the road resurfacing project done in 2017 and it will also extend the life of Wisteria and Kensington by an additional 20 years.

Starting this week, the City’s contractor, Brandt Construction, will begin doing work “behind the curb” – primarily marking and preparing driveway entrances so they can be rebuilt to match the new road height. Brandt will notify residents at least 24 hours in advance of any work that will be done to their driveway and accommodations will be made, as needed, to provide residents with access to their home.

The major work done in the streets is currently slated to begin around June 8th – after the scheduled end of school. Depending on decisions made by the Pleasant Valley School District, that date may be moved up.

The over-arching concern is to make sure residents and school vehicles are able to enter and exit the Havens Acres subdivision safely and with minimal confusion.

“If we can move the construction schedule up and get the road done sooner because kids are schooling from home, that would be preferred,” explained Mayor Mike Bawden. “Compacting the construction schedule not only reduces the congestion that always occurs around road projects, it could save us some money by allowing the contractor to be more efficient.”

The project was bid on a time and materials basis and is estimated to run around $223,000 in total. MSA Professional Services is overseeing the project on the City’s behalf.